By Sam Escolano | August 2026
Despite weather disturbances experienced last August, NLEX Segment 8.2 Section 1A is nearing completion and is intended to be opened to motorists this September 2026.
Throughout August, Quezon City and the greater Metro Manila area were affected by persistent southwest monsoon (Habagat) rains, intensified by several tropical weather systems that brought periods of heavy rainfall, localized flooding, and work disruption. These conditions impacted construction activities and required the project team to manage site operations, maintain safety protocols, and adjust activities to minimize delays. Despite these challenges, the team remained focused on meeting key project milestones, demonstrating resilience and commitment in advancing the project toward completion.
As of August 30, 2026, the project has reached 92.30% completion. Upon attaining substantial completion and receiving certification from the Independent Certification Engineer and the Toll Regulatory Board that the facility is commercially operable and safe for motorists, NLEX Segment 8.2 Section 1A will be opened to traffic.
Section 1A, extending from Mindanao Avenue to Quirino Highway, comprises the first 2-kilometer portion of the 11.3-kilometer NLEX Segment 8.2 Project. This initial segment marks an important milestone in the development of the entire Project, which will ultimately connect NLEX to C.P. Garcia Avenue in Katipunan, Quezon City, significantly enhancing mobility and connectivity within Metro Manila.